Show/Hide Menu
Hide/Show Apps
Logout
Türkçe
Türkçe
Search
Search
Login
Login
OpenMETU
OpenMETU
About
About
Open Science Policy
Open Science Policy
Open Access Guideline
Open Access Guideline
Postgraduate Thesis Guideline
Postgraduate Thesis Guideline
Communities & Collections
Communities & Collections
Help
Help
Frequently Asked Questions
Frequently Asked Questions
Guides
Guides
Thesis submission
Thesis submission
MS without thesis term project submission
MS without thesis term project submission
Publication submission with DOI
Publication submission with DOI
Publication submission
Publication submission
Supporting Information
Supporting Information
General Information
General Information
Copyright, Embargo and License
Copyright, Embargo and License
Contact us
Contact us
An activity-based lessons learned model to support scheduling decisions in construction
Date
2025-01-01
Author
Yılmaz, Anıl
Akcay, Emre Caner
Dikmen Toker, İrem
Birgönül, Mustafa Talat
Metadata
Show full item record
This work is licensed under a
Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License
.
Item Usage Stats
14
views
0
downloads
Cite This
Purpose: The aim of this study is to develop an activity-based lessons-learned model that allows construction companies to capture, store, classify and reuse activity-related lessons learned (LL) from previous projects, thereby increasing the reliability of time estimates in scheduling. Design/methodology/approach: Scheduling is a knowledge-intensive process that requires the utilization of data and expert opinion elicitation from various levels of an organization in construction projects. This research consists of five successive steps: performing a needs analysis, proposing an activity-based lessons-learned process model, validating the proposed process model, developing a tool to apply the proposed model in a computer environment and testing the applicability of the tool. To implement the proposed model in practice, a web-based tool, namely the Construction Industry Scheduling with Activity-Based Lessons Learned Tool (ConSALL Tool), was developed. Its functionality was evaluated using black-box testing. The tool was then applied in a real construction project. Findings: Results show that ConSALL has the potential to improve scheduling decisions in construction projects by incorporating data and experience from previous projects. Findings from this research can be used to develop similar models and AI tools to foster activity-based learning in other project-based industries as well as the construction industry. Originality/value: This paper presents an innovative approach to enhancing construction project scheduling by leveraging LL from past projects. The development and application of the ConSALL Tool demonstrate a practical implementation of the proposed model, providing a framework that can be adapted to other industries to improve project planning and execution.
Subject Keywords
Construction project
,
Knowledge management
,
Lessons learned
,
Scheduling
,
Web-based tool
URI
https://www.scopus.com/inward/record.uri?partnerID=HzOxMe3b&scp=105002433534&origin=inward
https://hdl.handle.net/11511/114280
Journal
Engineering, Construction and Architectural Management
DOI
https://doi.org/10.1108/ecam-06-2024-0729
Collections
Department of Civil Engineering, Article
Citation Formats
IEEE
ACM
APA
CHICAGO
MLA
BibTeX
A. Yılmaz, E. C. Akcay, İ. Dikmen Toker, and M. T. Birgönül, “An activity-based lessons learned model to support scheduling decisions in construction,”
Engineering, Construction and Architectural Management
, pp. 0–0, 2025, Accessed: 00, 2025. [Online]. Available: https://www.scopus.com/inward/record.uri?partnerID=HzOxMe3b&scp=105002433534&origin=inward.