Show/Hide Menu
Hide/Show Apps
Logout
Türkçe
Türkçe
Search
Search
Login
Login
OpenMETU
OpenMETU
About
About
Open Science Policy
Open Science Policy
Communities & Collections
Communities & Collections
Help
Help
Frequently Asked Questions
Frequently Asked Questions
Guides
Guides
Thesis submission
Thesis submission
MS without thesis term project submission
MS without thesis term project submission
Publication submission with DOI
Publication submission with DOI
Publication submission
Publication submission
Supporting Information
Supporting Information
General Information
General Information
Copyright, Embargo and License
Copyright, Embargo and License
Contact us
Contact us
Hybrid methods in intelligent control
Download
082792.pdf
Date
1999
Author
Tuncay, Serhat
Metadata
Show full item record
Item Usage Stats
53
views
0
downloads
Cite This
URI
https://hdl.handle.net/11511/2405
Collections
Graduate School of Natural and Applied Sciences, Thesis
Suggestions
OpenMETU
Core
Hybrid Optimization Method for Large-Scale Multimode Resource-Constrained Project Scheduling Problem
Sönmez, Rifat (2016-11-01)
Despite many research efforts that have focused on the multimode resource-constrained project scheduling problem (MRCPSP), very little success has been achieved in solving the problem for large-scale projects. In this paper a new hybrid optimization method is presented to achieve an advancement in optimal planning and scheduling of large-scale construction projects with multiple duration/resource execution modes and resource constraints. The proposed method consists of a novel heuristic and unique genetic o...
Hybrid wavelet-neural network models for time series data
Kılıç, Deniz Kenan; Uğur, Ömür; Department of Financial Mathematics (2021-3-3)
The thesis aims to combine wavelet theory with nonlinear models, particularly neural networks, to find an appropriate time series model structure. Data like financial time series are nonstationary, noisy, and chaotic. Therefore using wavelet analysis helps better modeling in the sense of both frequency and time. S&P500 (∧GSPC) and NASDAQ (∧ IXIC) data are divided into several components by using multiresolution analysis (MRA). Subsequently, each part is modeled by using a suitable neural network structure. ...
Hybrid heuristic algorithms for the multi objective load balancing of 2D bin packing problems
Muhammet, Beyaz; Dökeroğlu, Tansel; Coşar, Ahmet (null; 2015-09-23)
2D Bin packing problem (2DBPP) is an NP-hard combinatorial optimization problem. Multiobjective versions of this well-known industrial engineering problem can occur frequently in real world application. Recently, Hybrid Evolutionary Algorithms have appear as a new area of research with their ability to combine alternative heuristics and local search mechanisms together for higher quality solutions. In this study, we propose a set of novel multiobjective hybrid genetic and memetic algorithms that make use of...
Hybrid learning algorithm for intelligent short-term load forecasting
Kumluca Topallı, Ayça; Erkmen, İsmet; Department of Electrical and Electronics Engineering (2003)
Short-term load forecasting (STLF) is an important part of the power generation process. For years, it has been achieved by traditional approaches stochastic like time series; but, new methods based on artificial intelligence emerged recently in literature and started to replace the old ones in the industry. In order to follow the latest developments and to have a modern system, it is aimed to make a research on STLF in Turkey, by neural networks. For this purpose, a method is proposed to forecast Turkey̕s ...
Hybrid meta-heuristic algorithms for the resource constrained multi-project scheduling problem
Uysal, Furkan; Sönmez, Rifat; Department of Civil Engineering (2014)
The general resource constrained multi-project scheduling problem (RCMPSP) consists of simultaneous scheduling of two or more projects with common resource constraints, while minimizing duration of the projects. Critical Path Method and other scheduling methods do not consider resource conflicts and practically used commercial project management software packages and heuristic methods provide very limited solutions for the solution of the RCMPSP. Considering the practical importance of multi-project schedul...