Show/Hide Menu
Hide/Show Apps
Logout
Türkçe
Türkçe
Search
Search
Login
Login
OpenMETU
OpenMETU
About
About
Open Science Policy
Open Science Policy
Open Access Guideline
Open Access Guideline
Postgraduate Thesis Guideline
Postgraduate Thesis Guideline
Communities & Collections
Communities & Collections
Help
Help
Frequently Asked Questions
Frequently Asked Questions
Guides
Guides
Thesis submission
Thesis submission
MS without thesis term project submission
MS without thesis term project submission
Publication submission with DOI
Publication submission with DOI
Publication submission
Publication submission
Supporting Information
Supporting Information
General Information
General Information
Copyright, Embargo and License
Copyright, Embargo and License
Contact us
Contact us
A message handling system implementation X-400 on token ring
Download
010503.pdf
Date
1990
Author
Yardım, Yavuz
Metadata
Show full item record
Item Usage Stats
103
views
0
downloads
Cite This
URI
https://hdl.handle.net/11511/8274
Collections
Graduate School of Natural and Applied Sciences, Thesis
Suggestions
OpenMETU
Core
A graphical processing unit-based parallel hybrid genetic algorithm for resource-constrained multi-project scheduling problem
Uysal, Furkan; Sönmez, Rifat; İŞLEYEN, SELÇUK KÜRŞAT (2021-03-01)
In this article, we present a parallel graphical processing unit (GPU)-based genetic algorithm (GA) for solving the resource-constrained multi-project scheduling problem (RCMPSP). We assumed that activity pre-emption is not allowed. Problem is modeled in a portfolio of projects where precedence and resource constraints affect the portfolio duration. We also assume that the durations, availability of resources are deterministic and portfolio has a static nature. The objective in this article is to find a sta...
A SUPPORT VECTOR MACHINE METHOD FOR BID/NO BID DECISION MAKING
Sönmez, Rifat (2017-01-01)
The bid/no bid decision is an important and complex process, and is impacted by numerous variables that are related to the contractor, project, client, competitors, tender and market conditions. Despite the complexity of bid decision making process, in the construction industry the majority of bid/no bid decisions is made informally based on experience, judgment, and perception. In this paper, a procedure based on support vector machines and backward elimination regression is presented for improving the exi...
A set-based execution model for parallel prolog
Aybay, Işık; Baray, Mehmet; Bilgen, Semih; Department of Electrical and Electronics Engineering (1989)
A Mixed integer programming method for pareto front optimization of discrete time cost trade-off problem
Bilir, Mert; Sönmez, Rifat; Atan, S. Tankut; Department of Civil Engineering (2015)
There is a reverse relationship between the activity durations and costs in construction projects. In scheduling of construction projects, the project duration can be compressed (crashed) by expediting some of its activities in several ways including; increasing crew size, working overtime, or using alternative construction methods. As a result, when duration of a critical activity is decreased, its cost increases and project duration decreases. In construction projects, resources are usually available in d...
A partical implementation of data sublanguage alpha.
Baykara, Ramazan Ramiz; Department of Computer Engineering (1980)
Citation Formats
IEEE
ACM
APA
CHICAGO
MLA
BibTeX
Y. Yardım, “A message handling system implementation X-400 on token ring,” Middle East Technical University, 1990.