Show/Hide Menu
Hide/Show Apps
Logout
Türkçe
Türkçe
Search
Search
Login
Login
OpenMETU
OpenMETU
About
About
Open Science Policy
Open Science Policy
Open Access Guideline
Open Access Guideline
Postgraduate Thesis Guideline
Postgraduate Thesis Guideline
Communities & Collections
Communities & Collections
Help
Help
Frequently Asked Questions
Frequently Asked Questions
Guides
Guides
Thesis submission
Thesis submission
MS without thesis term project submission
MS without thesis term project submission
Publication submission with DOI
Publication submission with DOI
Publication submission
Publication submission
Supporting Information
Supporting Information
General Information
General Information
Copyright, Embargo and License
Copyright, Embargo and License
Contact us
Contact us
Congestion-driven transmission planning considering incentives for generator investments
Download
index.pdf
Date
2008
Author
Tör, Osman Bülent
Metadata
Show full item record
Item Usage Stats
174
views
57
downloads
Cite This
This thesis study focuses on transmission expansion planning (TEP) problem for restructured power systems and addresses challenges specifically in countries where electricity market is in developing phase after liberalization of power industry for establishing a competitive market, like Turkey. A novel multi-year TEP approach is developed which considers generation investment cost and transmission congestion level in the planning horizon. The model assesses the impact of generation investments on TEP problem. Benders decomposition methodology is utilized successfully to decompose the complex mixed-integer programming TEP problem into a master problem and two subproblems. Security subproblem assesses single-contingency criteria. Transmission congestion cost is considered within operational subproblem given that congestion level is a proper criterion for measuring competitiveness level of an electricity market. The proposed approach is applied to the Turkish power system. The proposed approach could be utilized to provide indicative plans, which might be quite necessary particularly during development of a competitive market. However, there is no guarantee that independent power producers (IPPs) will follow those plans which concern the maximization of social-welfare. Given the necessity of coordinating monopoly transmission and decentralized generator investment decisions, the proposed approach is improved further to include promoting decentralized generator investments through incentive payments. Such incentives might be necessary to trigger IPPs earlier than their projections, as illustrated by numerical examples including IEEE 30-bus system.
Subject Keywords
Electrical engineering.
,
Mathematical analysis.
URI
http://etd.lib.metu.edu.tr/upload/12609625/index.pdf
https://hdl.handle.net/11511/18288
Collections
Graduate School of Natural and Applied Sciences, Thesis
Suggestions
OpenMETU
Core
Congestion-Driven Transmission Planning Considering the Impact of Generator Expansion
Tor, Osman; Güven, Ali Nezih; Shahidehpour, Mohammad (2008-01-01)
This paper presents a multi-year transmission expansion planning (TEP) model which considers the transmission congestion and the impact of generation investment cost in the planning horizon. The Benders decomposition approach is utilized which decomposes TEP into a master problem and two subproblems representing security and optimal operation. The operation cost due to congestion (OCC) is considered in the proposed model given that the congestion level is a proper criterion for measuring the degree of compe...
Congestion-driven transmission planning considering the impact of generator expansion
TOR, Osman Bulent; Güven, Ali Nezih; Shahidehpour, Mohammad (2008-05-01)
This paper presents a multi-year transmission expansion planning (TEP) model which considers the transmission congestion and the impact of generation investment cost in the planning horizon. The Benders decomposition approach is utilized which decomposes TEP into a master problem and two subproblems representing security and optimal operation. The operation cost due to congestion (OCC) is considered in the proposed model given that the congestion level is a proper criterion for measuring the degree of compe...
The effects of hydro power plants’ governor settings on the turkish power system frequency
Cebeci, Mahmut Erkut; Ertaş, Arif; Department of Electrical and Electronics Engineering (2008)
This thesis proposes a method and develops a mathematical model for determining the effects of hydro power plants’ governor settings on the Turkish power system frequency. The Turkish power system suffers from frequency oscillations with 20 30 seconds period. Besides various negative effects on power plants and customers, these frequency oscillations are one of the most important obstacles before the interconnection of the Turkish power system with the UCTE (Union for the Coordination of Transmission of El...
Undesirable and semi-desirable facility location problems
Nadirler, Deniz; Karasakal, Esra; Department of Industrial Engineering (2004)
In this thesis, single undesirable and semi-desirable facility location problems are analyzed in a continuous planar region considering the interaction between the facility and the existing demand points. In both problems, the distance between the facility and the demand points is measured with the rectilinear metric. The aim in the first part where the location of a pure undesirable facility is considered, is to maximize the distance of the facility from the closest demand point. In the second part, where ...
A hybrid methodology in process modeling: “from-to chart based process discovery”
Esgin, Eren; Karagöz, Pınar; Department of Information Systems (2009)
The managing of complex business processes, which are changed due to globalization, calls for the development of powerful information systems that offer generic process modeling and process execution capabilities. Even though contemporary information systems are more and more utilized in enterprises, their actual impact in automatizing complex business process is still limited by the difficulties encountered in design phase. Actually this design phase is time consuming, often subjective and incomplete. In t...
Citation Formats
IEEE
ACM
APA
CHICAGO
MLA
BibTeX
O. B. Tör, “Congestion-driven transmission planning considering incentives for generator investments,” Ph.D. - Doctoral Program, Middle East Technical University, 2008.