Comparison of parametric models for conceptual duration estimation of building projects

Download
2008
Helvacı, Aziz
Estimation of construction durations is a very crucial part of project planning, as several key decisions are based on the estimated durations. In general, construction durations are estimated by using planning and scheduling techniques such as Gannt or bar chart, the Critical Path Method (CPM), and the Program Evaluation and Review Technique (PERT). However, these techniques usually require detailed design information for estimation of activity durations and determination of the sequencing of the activities. In some cases, pre-design duration estimates may be performed by using these techniques, however, accuracy of these estimates mainly depends on the experience of the planning engineer. In this study, it is aimed to develop and compare alternative methods for conceptual duration estimation of building constructions with basic data information available at the early stages of projects. Five parametric duration estimation models are developed with the data of 17 building projects which were constructed by a contractor in United States. Regression analysis and artificial neural networks are used in the development of these five duration estimation models. A parametric cost estimation model is developed using regression analysis for cost estimations to be used in calculating the prediction performances of cost based duration estimation models. Finally, prediction performances of all parametric duration estimation models are determined and compared. The models provided reasonably accurate estimates for construction durations. The results also indicated that construction durations can be predicted accurately without making an estimate for the project cost.

Suggestions

Cost estimation of trackworks of light rail and metro projects
Öztürk, Erhan; Gündüz, Murat; Department of Civil Engineering (2009)
The main objective of this work is to develop models using multivariable regression and artificial neural network approaches for cost estimation of the construction costs of trackworks of light rail transit and metro projects at the early stages of the construction process in Turkey. These two approaches were applied to a data set of 16 projects by using seventeen parameters available at the early design phase. According to the results of each method, regression analysis estimated the cost of testing sample...
A Method to decrease common problems in effort data collection in the software industry
Özkaya Eren, Ayşegül; Demirörs, Onur; Department of Information Systems (2012)
Efficient project planning and project management is crucial to complete the software projects in expected time and requirements. The most critical stage in project planning is estimation of the software size, time and budget. In this stage, effort data is used for benchmarking data sets, effort estimation, project monitoring and controlling. However, there are some problems related to effort data collection in the software industry. In this thesis, a pilot study and survey study are conducted to observe co...
A probabilistic schedule delay analysis in construction projects by using fuzzy logic incorporated with relative importance index (RII) method
Özdemir, Mustafa; Gündüz, Murat; Department of Civil Engineering (2010)
The aim of this thesis is to propose a decision support tool for contractors before the bidding stage to quantify the probability of schedule delay in construction projects by using fuzzy logic incorporated with relative importance index (RII) method. Eighty three (83) different schedule delay factors were identified through detailed literature review and interview with experts from a leading Turkish construction company, then categorized into nine (9) groups and visualized by utilizing Ishikawa (Fish Bone)...
A critical review of risk management support tools
Dikmen Toker, İrem; Birgönül, Mustafa Talat (null; 2004-09-03)
It has been claimed by many researchers that "a risk driven approach" to project management is necessary to increase the success of construction projects. Literature is very rich in conceptual frameworks to overcome the informality of risk management efforts. However, risk management paradigms exist as methodologies rather than systems which can fully support the risk management process. The existing risk management support tools are usually based on quantitative risk analysis whereas the other phases are c...
A Support vector regression method for conceptual cost estimate of construction projects
Yolasığmaz, İsmet Berki; Sönmez, Rifat; Department of Civil Engineering (2015)
Conceptual cost estimate is very important for initial project decisions when the design information is limited and the scope is not finalized at the early stages of the construction projects. It has serious effects on planning, design, cost management and budgeting. Therefore, the decision makers should be as accurate as possible while estimating the conceptual cost at the initial stage since a misestimation on the conceptual cost may lead to serious problems during feasibility analysis or at the later sta...
Citation Formats
A. Helvacı, “Comparison of parametric models for conceptual duration estimation of building projects,” M.S. - Master of Science, Middle East Technical University, 2008.