A Mixed linear integer model for military facility layout optimization problem

Download
2015
Ece, Hüseyin Bahadır
The positioning and layout of facilities on a construction site has a significant impact on productivity, costs, and duration of construction projects. The main objective of general construction site layout planning problem is to arrange the temporary facilities such as office buildings, residences, and warehouse in such a way that the construction activities can be performed with minimal costs. The military facility layout planning problem which considers layout of military facilities is similar to the construction site layout problem. This thesis presents a military facility layout model to optimize the distances that are frequently used both by military personnel and vehicles in their daily activities. Daily activities of military troops require continuous displacement according to the schedules in military terrain. Therefore, the model has been developed by considering the movement costs of the vehicles along with the distances travelled by the personnel. Moreover, the model established here considers vehicle types, vehicle and personnel quantities according to facility characters as well as distances between facilities and possible stations travelled on a monthly basis. Alternative zones for some stations have been included in the model to find the best placement for facilities and stations. Within this context, a mixed linear integer model is presented for the military facility layout problem. Then, the developed mixed integer formulation was solved by using AIMMS ver. 4.2. The results were compared with an already existing military facility layout planning method and advantages of the proposed model were discussed.

Suggestions

A Hybrid genetic algorithm for multi mode resource constrained scheduling problem for large size projects
Gürel, Mustafa; Sönmez, Rifat; Department of Civil Engineering (2015)
Just like in all industries, some of the available resources, in order to finish a project on time, are constrained in construction industry. To be able to finish the project on time has high importance both for the contractor and for the owner. Project scheduling in which resources are limited for a particular time are called as resource constrained project scheduling problems (RCPSP) and occupies a significant place in construction management. Especially for large scale projects, little success has been a...
A Comparative study on direct analysis method and effective length method in one-story semi-rigid frames
Bektaş, Şinasi; Birgönül, Mustafa Talat; Department of Civil Engineering (2012)
Many factors such as unforeseeable events, managerial or financial problems of Contractor, insufficient technical capacity of Engineer's site team and so on may lead to delays in construction projects. Proper analysis of compensability and quantum of a delay event is very important. Any delay analysis application can be considered as a result of the combination of contract documents, scheduler, record keeping mechanism at site, communication among project participants, delay analyst and delay analysis metho...
An Integrated regression-bootstrap sampling scheduling method for probabilistic duration range estimation of construction projects
Barış, Özgür; Sönmez, Rifat; Department of Civil Engineering (2019)
The estimation of project duration is important in construction projects, since it directly affects the costs and the success of the projects. Schedule risks can be determined along with the duration estimations in order to assess the possibility of delay penalties and additional costs. Therefore, the accuracy of the estimation of project duration range is very crucial in construction industry to assess the schedule risks. This thesis presents an integrated approach of non-parametric bootstrap sampling meth...
A Mixed integer programming method for integrated discrete time-cost trade-off and manpower resource leveling problem
Tatar, Ali Can; Sönmez, Rifat; Atan, S. Tankut; Department of Civil Engineering (2016)
Construction projects have to meet all of the objectives of scope, quality, schedule, budget simultaneously. These objectives, however, cannot be considered as independent of each other. For example, an increase in direct resources will usually lead to shorter activity durations. A shorter project duration results in lower indirect costs, whereas the additional resources cause an increase the project’s direct costs, in general. This phenomenon is defined as time-cost trade-off problem (TCTP). Nevertheless, ...
A Mixed integer programming method for pareto front optimization of discrete time cost trade-off problem
Bilir, Mert; Sönmez, Rifat; Atan, S. Tankut; Department of Civil Engineering (2015)
There is a reverse relationship between the activity durations and costs in construction projects. In scheduling of construction projects, the project duration can be compressed (crashed) by expediting some of its activities in several ways including; increasing crew size, working overtime, or using alternative construction methods. As a result, when duration of a critical activity is decreased, its cost increases and project duration decreases. In construction projects, resources are usually available in d...