Show/Hide Menu
Hide/Show Apps
Logout
Türkçe
Türkçe
Search
Search
Login
Login
OpenMETU
OpenMETU
About
About
Open Science Policy
Open Science Policy
Open Access Guideline
Open Access Guideline
Postgraduate Thesis Guideline
Postgraduate Thesis Guideline
Communities & Collections
Communities & Collections
Help
Help
Frequently Asked Questions
Frequently Asked Questions
Guides
Guides
Thesis submission
Thesis submission
MS without thesis term project submission
MS without thesis term project submission
Publication submission with DOI
Publication submission with DOI
Publication submission
Publication submission
Supporting Information
Supporting Information
General Information
General Information
Copyright, Embargo and License
Copyright, Embargo and License
Contact us
Contact us
A comparative study of regression analysis, neural networks and case-based reasoning for early range cost estimation of mass housing projects
Download
index.pdf
Date
2010
Author
Karancı, Hüseyin
Metadata
Show full item record
Item Usage Stats
303
views
151
downloads
Cite This
Construction cost estimating is essential for all of the stakeholders of a construction project from the beginning stage to the end. At early stages of a construction project, the design information and scope definition are very limited, hence; during conceptual (early) cost estimation, achieving high accuracy is very difficult. The level of uncertainty included in the cost estimations should be emphasized for making correct decisions throughout the dynamic stages of construction project management process, especially during early stages. By using range estimating, the level of uncertainties can be identified in cost estimations. This study represents integrations of parametric and probabilistic cost estimation techniques in a comparative base. Combinations of regression analysis, neural networks, case – based reasoning and bootstrap method are proposed for the conceptual (early) range cost estimations of mass housing projects. Practical methods for early range cost estimation of mass housing projects are provided for construction project management professionals. The methods are applied using bid offers of a Turkish contractor given for 41 mass housing projects. The owner of all projects is Housing Development Administration of Turkey (TOKI). The mass housing projects of TOKI are generally a mix of apartment blocks, social, health and educational facilities, and some projects may also have mosques. Results of the three different approaches are compared for predictive accuracy and predictive variability, and suggestions for early range cost estimation of construction projects are made.
Subject Keywords
Regression analysis.
,
Neural networks.
URI
http://etd.lib.metu.edu.tr/upload/12612514/index.pdf
https://hdl.handle.net/11511/20148
Collections
Graduate School of Natural and Applied Sciences, Thesis
Suggestions
OpenMETU
Core
An Integrated regression-bootstrap sampling scheduling method for probabilistic duration range estimation of construction projects
Barış, Özgür; Sönmez, Rifat; Department of Civil Engineering (2019)
The estimation of project duration is important in construction projects, since it directly affects the costs and the success of the projects. Schedule risks can be determined along with the duration estimations in order to assess the possibility of delay penalties and additional costs. Therefore, the accuracy of the estimation of project duration range is very crucial in construction industry to assess the schedule risks. This thesis presents an integrated approach of non-parametric bootstrap sampling meth...
A Support vector regression method for conceptual cost estimate of construction projects
Yolasığmaz, İsmet Berki; Sönmez, Rifat; Department of Civil Engineering (2015)
Conceptual cost estimate is very important for initial project decisions when the design information is limited and the scope is not finalized at the early stages of the construction projects. It has serious effects on planning, design, cost management and budgeting. Therefore, the decision makers should be as accurate as possible while estimating the conceptual cost at the initial stage since a misestimation on the conceptual cost may lead to serious problems during feasibility analysis or at the later sta...
Comparison of parametric models for conceptual duration estimation of building projects
Helvacı, Aziz; Sönmez, Rifat; Department of Civil Engineering (2008)
Estimation of construction durations is a very crucial part of project planning, as several key decisions are based on the estimated durations. In general, construction durations are estimated by using planning and scheduling techniques such as Gannt or bar chart, the Critical Path Method (CPM), and the Program Evaluation and Review Technique (PERT). However, these techniques usually require detailed design information for estimation of activity durations and determination of the sequencing of the activitie...
A SUPPORT VECTOR MACHINE METHOD FOR BID/NO BID DECISION MAKING
Sönmez, Rifat (2017-01-01)
The bid/no bid decision is an important and complex process, and is impacted by numerous variables that are related to the contractor, project, client, competitors, tender and market conditions. Despite the complexity of bid decision making process, in the construction industry the majority of bid/no bid decisions is made informally based on experience, judgment, and perception. In this paper, a procedure based on support vector machines and backward elimination regression is presented for improving the exi...
A polynomial algorithm for the earthwork allocation problem with borrow and waste site selection
Guden, Huseyin; Süral, Haldun (2017-09-01)
In road construction projects, earthwork is planned together with horizontal and vertical alignments. This study focuses on earthwork operations that basically include cutting the hills and filling the holes on the road path. The candidate borrow and waste sites can also be used to obtain or heap earth when the available cut and fill amounts are not balanced or operating these sites reduces the total earthwork cost. Total earthwork cost contains the transportation cost and the overall cost related to openin...