Show/Hide Menu
Hide/Show Apps
Logout
Türkçe
Türkçe
Search
Search
Login
Login
OpenMETU
OpenMETU
About
About
Open Science Policy
Open Science Policy
Open Access Guideline
Open Access Guideline
Postgraduate Thesis Guideline
Postgraduate Thesis Guideline
Communities & Collections
Communities & Collections
Help
Help
Frequently Asked Questions
Frequently Asked Questions
Guides
Guides
Thesis submission
Thesis submission
MS without thesis term project submission
MS without thesis term project submission
Publication submission with DOI
Publication submission with DOI
Publication submission
Publication submission
Supporting Information
Supporting Information
General Information
General Information
Copyright, Embargo and License
Copyright, Embargo and License
Contact us
Contact us
Heuristic and exact methods for the large-scale discrete time-cost trade-off problems
Download
index.pdf
Date
2018
Author
Aminbakhsh, Saman
Metadata
Show full item record
Item Usage Stats
343
views
124
downloads
Cite This
Construction industry necessitates formulating impeccable plans by decision makers for securing optimal outcomes. Managers often face the challenge of compromising between diverse and usually conflicting objectives. Particularly, accurate decisions on the time and cost must be made in every construction project since project success is chiefly related to these objectives. This is realized by addressing the time-cost trade-off problem (TCTP) which is an optimization problem and its objective is to identify the set of time-cost alternatives that provide the optimal schedule(s). Due to discreteness of many resources in realistic projects, discrete version of this problem (DTCTP) is of great practical relevance. The Pareto front extension of DTCTP is a multi-objective optimization problem that facilities preference articulation of decision makers by providing them with a set of mutually non-dominated solutions of same quality. Due to the complex nature of DTCTP, the literature on large-scale problems is virtually void; besides, most of the existing methods do not suit actual practices and popular commercial planning software lack tools for solution of DTCTP. The main focus of this thesis relates to providing means for optimization of real-life-scale Pareto oriented DTCTPs and it aims to contribute to both researchers and practitioners by tightening the gap between the literature and the real-world requirements of the projects. The results of the comparative studies reveal that the proposed methods are successful for solving large-scale DTCTPs and provide the management with a quantitative basis for decisions on selection of the proper alternatives for the real-life-scale construction projects.
Subject Keywords
Construction industry.
,
Construction projects.
,
Construction industry
,
Construction industry
URI
http://etd.lib.metu.edu.tr/upload/12622120/index.pdf
https://hdl.handle.net/11511/27326
Collections
Graduate School of Natural and Applied Sciences, Thesis
Suggestions
OpenMETU
Core
Awareness of the Turkish construction industry towards industry 4.0 technologies and concepts
Ebrahimi, Shima; Dikmen Toker, İrem; Department of Civil Engineering (2019)
The Architecture, Engineering and Construction (AEC) industry is a well-known latecomer to the effectiveness proposed by embracing of Industry 4.0 technologies; while other sectors embrace digitization and Information Communication Technologies (ICT) as an innovative strategy for maintaining economic profit and efficiency. In spite of the potential benefits that proposed by Industry 4.0, this revolution was not able to gain enough attention in the construction industry. Therefore, this study took initial st...
Development of an IT-based tool for portfolio assessment and management for construction companies
Bilgin, Gözde; Dikmen Toker, İrem; Özorhon Orakçal, Beliz; Department of Civil Engineering (2019)
Development in the construction industry has leaded most of the construction companies to undertake more complex projects than before, which are generally executed concurrently. Therefore, project management routines of the companies may not support effective management of multi-projects. Project portfolio management approach has been suggested to meet requirements for coordinating multi-projects to meet strategic objectives under limited resources. Since project portfolio management requires a comprehensiv...
A Hybrid genetic algorithm for multi mode resource constrained scheduling problem for large size projects
Gürel, Mustafa; Sönmez, Rifat; Department of Civil Engineering (2015)
Just like in all industries, some of the available resources, in order to finish a project on time, are constrained in construction industry. To be able to finish the project on time has high importance both for the contractor and for the owner. Project scheduling in which resources are limited for a particular time are called as resource constrained project scheduling problems (RCPSP) and occupies a significant place in construction management. Especially for large scale projects, little success has been a...
Motivators and barriers for green building construction market in Turkey
Gündoğan, Handan; Aydın, İsmail; Altan Sakarya, Ayşe Burcu; Department of Civil Engineering (2012)
‘Green Buildings’ play an important role to increase the implementation of sustainable strategies in the construction industry. Although there is a process of change within Turkish building environment towards implementation of green strategies nowadays, limited research has been conducted to search the reasons that drive the market and the important barriers that block the green building movement. This thesis is intended to fill this gap in the literature and contribute to the field of knowledge regarding ...
A Support vector regression method for conceptual cost estimate of construction projects
Yolasığmaz, İsmet Berki; Sönmez, Rifat; Department of Civil Engineering (2015)
Conceptual cost estimate is very important for initial project decisions when the design information is limited and the scope is not finalized at the early stages of the construction projects. It has serious effects on planning, design, cost management and budgeting. Therefore, the decision makers should be as accurate as possible while estimating the conceptual cost at the initial stage since a misestimation on the conceptual cost may lead to serious problems during feasibility analysis or at the later sta...