Show/Hide Menu
Hide/Show Apps
Logout
Türkçe
Türkçe
Search
Search
Login
Login
OpenMETU
OpenMETU
About
About
Open Science Policy
Open Science Policy
Open Access Guideline
Open Access Guideline
Postgraduate Thesis Guideline
Postgraduate Thesis Guideline
Communities & Collections
Communities & Collections
Help
Help
Frequently Asked Questions
Frequently Asked Questions
Guides
Guides
Thesis submission
Thesis submission
MS without thesis term project submission
MS without thesis term project submission
Publication submission with DOI
Publication submission with DOI
Publication submission
Publication submission
Supporting Information
Supporting Information
General Information
General Information
Copyright, Embargo and License
Copyright, Embargo and License
Contact us
Contact us
Construction labor productivity modeling with neural networks
Date
1998-11-01
Author
Sönmez, Rifat
Metadata
Show full item record
This work is licensed under a
Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License
.
Item Usage Stats
172
views
0
downloads
Cite This
Construction labor productivity is affected by several factors. Modeling of construction labor productivity could be challenging when effects of multiple factors are considered simultaneously. In this paper a methodology based on the regression and neural network modeling techniques is presented for quantitative evaluation of the impact of multiple factors on productivity. The methodology is applied to develop productivity models for concrete pouring, formwork, and concrete finishing tasks, using data compiled from eight building projects. The predictive behaviors of the models are compared with the previous productivity studies. Model results, advantages of the methodology, and study limitations are discussed.
Subject Keywords
Strategy and Management
,
Industrial relations
,
Civil and Structural Engineering
,
Building and Construction
URI
https://hdl.handle.net/11511/56297
Journal
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE
DOI
https://doi.org/10.1061/(asce)0733-9364(1998)124:6(498)
Collections
Department of Civil Engineering, Article
Suggestions
OpenMETU
Core
Delay Risk Assessment of Repetitive Construction Projects Using Line-of-Balance Scheduling and Monte Carlo Simulation
Tokdemir, Onur Behzat; Dikmen Toker, İrem (American Society of Civil Engineers (ASCE), 2019-02-01)
Although the line-of-balance (LOB) method is widely used for the scheduling of repetitive construction projects, there are only a limited number of studies that deal with the issue of how to incorporate uncertainty in repetitive schedules. In this paper, a delay risk assessment method is proposed for projects scheduled by LOB. In the proposed method, a LOB schedule is prepared considering the target rate of delivery, and then risk scenarios are defined considering the sources of uncertainty and vulnerabilit...
Integrated Approach to Overcome Shortcomings in Current Delay Analysis Practices
Birgönül, Mustafa Talat; Dikmen Toker, İrem (American Society of Civil Engineers (ASCE), 2015-04-01)
Many factors, such as unforeseeable events, managerial and financial problems of contractors, insufficient technical capacity of site teams of contractors or Consultants, and so on, may lead to delays in construction projects. Proper analysis of compensability and quantum of a delay event is of prime importance. Any delay analysis application can be considered as a result of the combination of contract documents, scheduler, record-keeping mechanism at the site, communication among project participants, dela...
Critical Sequence Crashing Heuristic for Resource-Constrained Discrete Time-Cost Trade-Off Problem
Sönmez, Rifat; Uysal, Furkan (American Society of Civil Engineers (ASCE), 2016-03-01)
Despite the importance of project deadlines and resource constraints in construction scheduling, very little success has been achieved in solving the resource-constrained discrete time-cost trade-off problem (RCDTCTP), especially for large-scale projects. In this paper a new heuristic method is designed and developed to achieve fast and high-quality solutions for the large-scale RCDTCTP. The proposed method is based on the novel principles to enable effective exploration of the search space through adequate...
Context-Dependent Construction Conflict Management Performance Analysis Based on Competency Theory
Altuncan, Izel Unsal; Tanyer, Ali Murat (American Society of Civil Engineers (ASCE), 2018-12-01)
Construction project environments are shaped by uncertainty and complexity; therefore, conflict situations that lead to time and cost overruns are rather frequent. However, no empirical studies conducted so far have analyzed conflict management performances of individuals on a context-dependent basis. This paper proposes a performance assessment methodology for conflict management that integrates two different approaches from other disciplines: hypothetical situations and competency theory. The approach ana...
Activity Uncrashing Heuristic with Noncritical Activity Rescheduling Method for the Discrete Time-Cost Trade-Off Problem
Sönmez, Rifat; Atan, Tankut (American Society of Civil Engineers (ASCE), 2020-08-01)
Despite intensive research efforts that have been devoted to discrete time-cost optimization of construction projects, the current methods have very limited capabilities for solving the problem for real-life-sized projects. This study presents a new activity uncrashing heuristic with noncritical activity rescheduling method to narrow the gap between the research and practice for time-cost optimization. The uncrashing heuristic searches for new solutions by uncrashing the critical activities with the highest...
Citation Formats
IEEE
ACM
APA
CHICAGO
MLA
BibTeX
R. Sönmez, “Construction labor productivity modeling with neural networks,”
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE
, pp. 498–504, 1998, Accessed: 00, 2020. [Online]. Available: https://hdl.handle.net/11511/56297.