Show/Hide Menu
Hide/Show Apps
Logout
Türkçe
Türkçe
Search
Search
Login
Login
OpenMETU
OpenMETU
About
About
Open Science Policy
Open Science Policy
Open Access Guideline
Open Access Guideline
Postgraduate Thesis Guideline
Postgraduate Thesis Guideline
Communities & Collections
Communities & Collections
Help
Help
Frequently Asked Questions
Frequently Asked Questions
Guides
Guides
Thesis submission
Thesis submission
MS without thesis term project submission
MS without thesis term project submission
Publication submission with DOI
Publication submission with DOI
Publication submission
Publication submission
Supporting Information
Supporting Information
General Information
General Information
Copyright, Embargo and License
Copyright, Embargo and License
Contact us
Contact us
A robust time-cost-quality-energy-environment trade-off with resource-constrained in project management: A case study for a bridge construction project
Download
index.pdf
Date
2022-01-01
Author
Lotfi, Reza
Yadegari, Zahra
Hosseini, Seyed Hossein
Khameneh, Amir Hossein
Tirkolaee, Erfan Babaee
Weber, Gerhard Wilhelm
Metadata
Show full item record
This work is licensed under a
Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License
.
Item Usage Stats
166
views
165
downloads
Cite This
Sustainable development requires scheduling and implementation of projects by considering cost, environment, energy, and quality factors. Using a robust approach, this study investigates the time-cost-quality-energy-environment problem in executing projects and practically indicates its implementation capability in the form of a case study of a bridge construction project in Tehran, Iran. This study aims to take into account the sustainability pillars in scheduling projects and uncertainties in modeling them. To model the study problem, robust nonlinear programming (NLP) involving the objectives of cost, quality, energy, and pollution level is applied with resource-constrained. According to the results, as time diminished, the cost, energy, and pollution initially decreased and then increased, with a reduction in quality. To make the model close to the real world by considering uncertainties, the cost and quality tangibly improved, and pollution and energy consumption declined. We applied the augmented ε-constraint method to solve the proposed model. According to the result of the research, with regard to the time-cost, time-quality, time-energy, and time-pollution charts, as uncertainty increases, the cost and quality will improve, and pollution and energy will decrease. The proposed model can be employed for all industrial projects, including roads, construction, and manufacturing.
Subject Keywords
Augmented ε-Constraint Method
,
Multi-objective optimization
,
Robust optimization
,
Time-Cost-Quality-Energy-Environment Trade-off
URI
https://hdl.handle.net/11511/97723
Journal
Journal of Industrial and Management Optimization
DOI
https://doi.org/10.3934/jimo.2020158
Collections
Graduate School of Applied Mathematics, Article
Suggestions
OpenMETU
Core
An Exploratory Multi-Objective Retrofit Decision-Making Process
Akin, Şahin; Işeri, Orçun Koral; Erdogan, Bilge; Gürsel Dino, İpek (2020-08-18)
The retrofit processes for buildings necessitates long-term planning and costly operations and requires a collaborative approach where a high number of alternative solutions should be explored by stakeholders. However, the evaluation of a range of retrofit solutions is a complex process wherein various design parameters and objectives are involved. The identification of the most effective solutions requires a collaborative evaluation in order to satisfy all stakeholders‘ expectations; however, during the de...
Investigation of layout optimization for offshore wind farms and a case study for a region in Turkey
Kaya, Baran; Oğuz, Elif; Department of Civil Engineering (2022-2)
In this thesis, the focus was to develop an optimization tool by using mathematical layout optimization methods aiming to increase the energy capacity or reduce the cost of an offshore wind farm. For this purpose, two wind farm layout optimization (WFLO) models were developed using genetic algorithm (GA): model (a) minimizing the cost of power for variable turbine number, model (b) maximizing the power generation for fixed turbine number. Wind speed and wind direction were assumed constant. Therefore, unlik...
A mixed integer model for optimization of discrete time cost tradeoff problem
Tatar, Ali Can; Bilir, Mert; Sönmez, Rifat; Atan, Sabri Tankut (null; 2016-06-25)
In construction projects, activity durations can be expedited by allocating additional resources. Decreasing activity durations by means of crashing, usually leads to increase in the direct expenses. This trade-off between time and cost is called as the time-cost trade-off problem. Since in practice many resources are available in discrete units, numerous research has focussed on the discrete version of this problem called the discrete time-cost trade-off problem (DTCTP). Achieving the project schedule that...
An exploratory study on utilization of BIM for risk management
Kaya, Hazal Deniz; Dikmen, İrem; Atasoy, Güzide; Birgönül, Mustafa Talat (İstanbul Teknik Üniversitesi; 2020-11-14)
It is a well-known fact that BIM application in construction projects enables several advantages such as better collaboration and communication, effective project visualization before construction, more efficient cost estimation and scheduling, and an increase in productivity. Although many of these advantages that BIM contributes to construction projects may result in opportunities for better risk management, there are limited studies in the construction management literature that investigate this subject....
An Integrated regression-bootstrap sampling scheduling method for probabilistic duration range estimation of construction projects
Barış, Özgür; Sönmez, Rifat; Department of Civil Engineering (2019)
The estimation of project duration is important in construction projects, since it directly affects the costs and the success of the projects. Schedule risks can be determined along with the duration estimations in order to assess the possibility of delay penalties and additional costs. Therefore, the accuracy of the estimation of project duration range is very crucial in construction industry to assess the schedule risks. This thesis presents an integrated approach of non-parametric bootstrap sampling meth...
Citation Formats
IEEE
ACM
APA
CHICAGO
MLA
BibTeX
R. Lotfi, Z. Yadegari, S. H. Hosseini, A. H. Khameneh, E. B. Tirkolaee, and G. W. Weber, “A robust time-cost-quality-energy-environment trade-off with resource-constrained in project management: A case study for a bridge construction project,”
Journal of Industrial and Management Optimization
, vol. 18, no. 1, pp. 375–396, 2022, Accessed: 00, 2022. [Online]. Available: https://hdl.handle.net/11511/97723.